Progress Update: Week One

  • Hannah Redifer
  • Jul 17, 2016
  • 1 min read

This week our crew began working on the Sani-Freeze structure. We began framing for the front of the structure on Tuesday afternoon, and finished framing the two sides that will have windows on them. On Friday afternoon, we framed the center piece that will have the door, as well as the planters that will have the covering mimicking the original brick material. We also finished the side supports for the structure. In the photos, you can see members of our crew cutting wood for the studs and planter framing. The last two photos are the finished product from Friday afternoon.


 
 
 